Prudent CAPEX
Key investment projects
EVRAZ Pueblo seamless threading
The project aim is to in-source seamless threading and coupling process from third-party providers to improve cost competitiveness.
StatusEquipment installation completed and commissioning commenced in Q4 2018, first order shipped in December 2018.
CAPEX in 2018
US$15 million
EVRAZ Red Deer heat treatment
The project aim is to develop heat treatment capability to access a higher margin market.
StatusLaunched execution phase of the project.
CAPEX in 2018
US$13 million
Key maintenance projects
During 2018, the Group’s operations completed important maintenance projects:
- At EVRAZ Portland, cooling bed repairs and mill leveler rebuild were completed;
- At EVRAZ Pueblo, installed 2 new scrap cranes and repaired the furnace roof/hearth in the Seamless Mill;
- At EVRAZ Regina, EVRAZ carried out installation of a new transformer for the Steel mill.